Date Plus Business Days

Add working days to a date, skipping every Saturday and Sunday along the way.

LET’S WORK IT OUT

Your inputs

Format YYYY-MM-DD
Negative counts backwards

Results update as you type. Check the units before you begin.

View result ↓
YOUR RESULT
—
Working days
Adjust the inputs

Your result updates live as you type.

A ten-working-day turnaround is not ten calendar days. This calculator steps forward one day at a time and only counts a day towards the total when it falls Monday to Friday, so the answer reflects how the working week actually behaves. Ten working days from 10 August 2026 is Monday 24 August 2026, which is 14 calendar days later.

The gap between the two figures grows predictably. Every five working days consumes seven calendar days, so the calendar cost is roughly the working days multiplied by 1.4, with the exact figure depending on which weekday you start from. The extras name both counts so a service-level promise can be quoted in either.

Negative values count backwards through working days, which is how you find the latest date a task can start and still hit a deadline. Public holidays are not built in because they differ by country, so the count is a pure Monday-to-Friday figure you can then adjust.

The formula

Result = step forward one day at a time, counting only Mon–Fri until N are reached
S
Start date
N
Working days to add
R
Result date, always a weekday
ΔD
Calendar days consumed

How to use this calculator

  1. Enter the start date as YYYY-MM-DD.
  2. Enter the number of working days, negative to count backwards.
  3. The gauge shows the working days requested.
  4. The breakdown gives the result date, calendar days used and weekends crossed.

Worked examples

10 working days from 10 August 2026

The result is Monday 24 August 2026. That is 14 calendar days, because 4 weekend days were skipped on the way. A promise of "ten working days" therefore runs almost two full calendar weeks.

Why the start weekday matters

Five working days from Monday 10 August 2026 lands on 17 August 2026, using 7 calendar days. The same five days from Thursday 13 August lands on 20 August 2026, using 7 calendar days, because a weekend falls inside the span.

How to read your score

0–5Within a weekOne working week or less.
5–20Up to a monthOne to four working weeks.
20–60One to three monthsA quarter of working days at most.
60–—Over three monthsLong enough that public holidays will matter.

Frequently asked questions

Are public holidays excluded?

No, only Saturdays and Sundays. Holiday dates differ by country and region, so the honest answer is a clean weekday count that you then extend by the number of holidays in the window.

What if the start date is a Saturday?

The count begins from the following Monday in effect, because weekend days never count towards the total. The result date is always a Monday to Friday.

How do I find a latest start date?

Enter the deadline and a negative number of working days. The result is the last date on which work can begin and still finish on time.

Does the start date count as day one?

No. The result is N working days after the start date, so a value of 1 from a Monday gives the Tuesday. If your rule counts the start day, subtract one from the total.

Working day offsets from 10 August 2026

Working days converted to calendar dates
Working daysResult dateWeekdayCalendar days
111 August 2026Tuesday1
313 August 2026Thursday3
517 August 2026Monday7
1024 August 2026Monday14
1531 August 2026Monday21
207 September 2026Monday28
3021 September 2026Monday42
602 November 2026Monday84

Calendar days always exceed working days once a weekend falls inside the span.

Related calculators